Which practice helps mitigate delays caused by supply shortages?

Take your CIOB EPA Level 4 Design and Construction Management Test preparation to the next level. Practice with tailored quizzes, detailed explanations, and insightful hints. Prepare confidently for your upcoming assessment!

Multiple Choice

Which practice helps mitigate delays caused by supply shortages?

Explanation:
Securing materials early helps prevent delays when supply chains tighten. By initiating procurement early, you identify long-lead items and lock in orders well in advance, allowing suppliers to confirm availability and delivery windows. This creates a buffer in the schedule, reduces the risk of idle time waiting for materials, and helps the project stay on track even if shortages arise. Waiting to procure until items arrive leaves no slack, making the project vulnerable to delays if items aren’t readily available. Designing changes to manage risk often causes rework and additional time, and avoiding procurement planning ignores a critical step in controlling the schedule. Therefore, early procurement is the most effective approach.

Securing materials early helps prevent delays when supply chains tighten. By initiating procurement early, you identify long-lead items and lock in orders well in advance, allowing suppliers to confirm availability and delivery windows. This creates a buffer in the schedule, reduces the risk of idle time waiting for materials, and helps the project stay on track even if shortages arise. Waiting to procure until items arrive leaves no slack, making the project vulnerable to delays if items aren’t readily available. Designing changes to manage risk often causes rework and additional time, and avoiding procurement planning ignores a critical step in controlling the schedule. Therefore, early procurement is the most effective approach.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy