In Earned Value Management, what does Planned Value represent?

Take your CIOB EPA Level 4 Design and Construction Management Test preparation to the next level. Practice with tailored quizzes, detailed explanations, and insightful hints. Prepare confidently for your upcoming assessment!

Multiple Choice

In Earned Value Management, what does Planned Value represent?

Explanation:
Planned Value represents the budgeted cost of the work that should be completed by a specific date according to the project schedule. It is the time-phased portion of the baseline, showing what the plan expects you to have spent or allocated for the scheduled scope by that date. It’s derived from the total budget and the percent of work planned to be done by the date. For example, if the total budget is 1,000,000 and the plan calls for 25% of the work to be finished by the end of the period, Planned Value is 250,000. This differs from Earned Value, which measures the budgeted cost of actual work completed, and from Actual Cost, which is what has actually been spent. Using PV alongside EV and AC helps assess schedule performance; if EV is less than PV you’re behind plan, if EV matches PV you’re on plan.

Planned Value represents the budgeted cost of the work that should be completed by a specific date according to the project schedule. It is the time-phased portion of the baseline, showing what the plan expects you to have spent or allocated for the scheduled scope by that date. It’s derived from the total budget and the percent of work planned to be done by the date. For example, if the total budget is 1,000,000 and the plan calls for 25% of the work to be finished by the end of the period, Planned Value is 250,000. This differs from Earned Value, which measures the budgeted cost of actual work completed, and from Actual Cost, which is what has actually been spent. Using PV alongside EV and AC helps assess schedule performance; if EV is less than PV you’re behind plan, if EV matches PV you’re on plan.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy